254
|
1 3: will complete after meeting on 05/06
|
|
2 4: Fringe Society visited re office space planning; no money yet received;
|
|
3 FS accessibility visit next week
|
|
4 From David Sterratt:
|
|
5
|
|
6 We finalised the contract with the Fringe Society and both parties have
|
|
7 signed it. Regarding the issues raised in the last minutes: (1) We
|
|
8 agreed that the Fringe Society will have use of the meeting room from
|
|
9 1pm on a Sunday and that meeting house staff will be using the kitchen
|
|
10 up until 1.30pm. Friends will need to start departing at 12.45pm. (2)
|
|
11 The Fringe Society were content with the liberalised media clause we
|
|
12 proposed. (3) The Fringe Society did not, after all, want to use our AV
|
|
13 system.
|
|
14
|
|
15 We have liaised with the Fringe about operational details including
|
|
16 moving the furniture and internet/Wifi connectivity. The conversation
|
|
17 with the Fringe networking staff has led to us contacting User2
|
|
18 computing and learning how to administer the Wifi access points, which
|
|
19 has allowed us to set up a private network for the office and foyer
|
|
20 computers. However, the admin interface is set up on David Sterratt's
|
|
21 computer, and it may be desirable to install it on a meeting house
|
|
22 computer.
|
|
23
|
|
24 David Sterratt and Miranda have agreed with David Clarke and other
|
|
25 Friends attending 9.30 meeting that it will not be held in the meeting
|
|
26 house during the Fringe, but it can still be held on Zoom.
|
|
27
|
|
28 6a: Flat rental figures all in - see drop box folder in Affordability group.
|
|
29 7b: Wedding planning going well - IT an issue but we can work with what we
|
|
30 have - Emma & Andy aware when they booked what the MH provided
|
|
31 8a: quaker (old pw) and quaker-office (new, staff-only)
|
|
32 (8b: still getting 'mail undelivered' in the spam folder on office@ )
|
|
33 9b: GSM dialler was brought for install but the wrong sort, so still
|
|
34 awaiting installation
|
|
35 9c: Nothing to report
|
|
36 9d: no decision on carpets - impact of building changes / cafe could change
|
|
37 decision to be made
|
|
38 9e: no response from either firm - too busy or job too small - will develop
|
|
39 my own alternatives
|
|
40 11 bullet 3 continued
|
|