75 | 75 |
76 We will discuss with MG how the time between now and 1 July can | 76 We will discuss with MG how the time between now and 1 July can |
77 best be used to prepare staff for at least the necessary tasks. | 77 best be used to prepare staff for at least the necessary tasks. |
78 | 78 |
79 We are prepared to cover supervision and, if necessary, be present, | 79 We are prepared to cover supervision and, if necessary, be present, |
80 during the crucial weeks of period B: 14-19 July; 2--9 August; | 80 during the crucial weeks of period B: 14-19 July*; 2--9 August; |
81 24--31 August. | 81 24--31 August. [HST to check with Hartley about this -- will they |
82 actually be doing setup that week?] | |
82 | 83 |
83 | 84 |
84 5. Any other business | 85 5. Any other business |
85 | 86 |
86 5.1 John Renshaw will visit in the week beginning 27 May to begin | 87 5.1 John Renshaw will visit in the week beginning 27 May to begin |