1 Correspondance between Martin Ward (MW), Clerk to AM Trustees and John
2 Renshaw (JR), contracted to carry out the Quinquennial Review.
3
4 MW, 23 September:
5
6 Thank you for all of the documents which you sent through on 29th
7 August. While we were able to discuss these briefly at the meeting on
8 2nd September our trustees understandably wanted more time to consider
9 them before making substantive decisions. We have a further meeting
10 planned for 8th October, and if you were able to answer the following
11 questions before then it would be appreciated.
12 The QS's estimate of £90k for the courtyard work is far higher than the
13 indicative £22,750 in the QR. Does it cover additional work which is
14 not in the QR figure? Assuming the higher figure is the more reliable
15 trustees may be inclined to focus on weatherproofing work around the
16 courtyard and be more selective about replacement of windows. Would
17 you have a view on which windows should be a priority (in addition to
18 those to the creche area which you flagged as urgent in the QR)?
19 Within the weatherproofing work would you be able to advise on what
20 proportion might reasonably be requested from the owners of the other
21 properties which would benefit?
22
23 JR, 6 October:
24
25 The budget cost prepared by Gus Simpson of Ralph Ogg & Partners
26 chartered quantity surveyors includes more extensive work than is
27 covered by the QFR and also won’t include inflation since the draft
28 report was issued. Also apologies for not making it clearer - this
29 cost also includes repairs and re-decoration of the neighbours
30 windows c. £9k. There is also a contingency sum of£11,740 which
31 isn’t included in the QFR budget cost and the budget costs don't
32 include a full allowance for preliminaries. I assume that the
33 adjoining proprietors will have a shared responsibility for the
34 repairs to the external fabric of the tenement. I assume that the
35 works would be carried out in a similar way to the external repairs
36 to the front elevation of Upper Bow undertaken in 2021 when the
37 condition of the windows was checked when safe full external access
38 was available, costs confirmed and repairs carried out once each
39 proprietor confirmed that they wanted to proceed.
40
41 MW:
42
43 We are interested in moving to improve the Bow Room, possibly as a
44 separate project which might attract funding and would rather not delay
45 that work by tying it in with the courtyard. How much synergy there
46 would be in practice between the two in terms of possible contractors
47 and access? We assume that work on the Bow Room would be carried out
48 from Upper Bow, whereas the scaffolding in the courtyard might be
49 approached (by agreement) from Riddle's Court. I had assumed that the
50 scaffolding would need to be taken through the common door to the flats
51 rather than down from the Lawnmarket/Riddle’s Court. Do you have
52 contact details of who needs to be asked if this is acceptable as it
53 may change the preliminary costs for the erection and removal of the
54 scaffolding? I am then happy to contact them. My assumption was that
55 the main contractors for the external fabric repairs could also manage
56 the internal works and it would be more efficient in terms of
57 contractors overheads to carry out the work at the same time. Please
58 let me know how you want to proceed.
59
60 MW:
61
62 Because of the possible uses of the Bow Room we feel that accessibility
63 from Upper Bow is more of an issue than access to the rest of the
64 meeting house. Would it be possible to cut a ramp into the floor
65 within the building to achieve level access to the existing pavement?
66 How would this work with an inward opening door? Rising hinges?
67
68 JR:
69
70 I think that the best solutions would either be to set the door back
71 and form a triangular ramp within the thickness of the external wall
72 or to discuss the possibility of altering the levels of the pavement
73 with the Council to form a level platt of Caithness stone outside
74 the entrance door which then slope downward to the south and west to
75 meet the existing pavement levels. I guess the cheapest option would
76 be to obtain and temporary triangular ramp which could be put in
77 place when needed. We designed a similar temporary ramp for a shop
78 on the South Bridge which was fixed to the side of the stall riser
79 and then folded down when needed. This is likely to require LBC
80 which would likely delay a start to the external repairs although we
81 could commit to applying for this before the end of October if you
82 want us to proceed. We would like to agree a finalised version of
83 the quinquennial report now, but the plans for the two flats should
84 be added in, page and section numbering checked (for example there
85 seems to be a gap in the summary between point (d) and point (g)),
86 and the estimate of costs may need to be adjusted in the light of
87 the QS assessment. I am finalising this at the moment with the
88 additional information to include the plans of the two flats and
89 their condition.