# HG changeset patch # User Henry Thompson # Date 1713535799 -3600 # Node ID e494ada70bea64597f6c6c2db9f3a7a8fa737fe8 # Parent 00d3097225207f0f179c565638a6884329e8d430 from notes.txt via pandoc diff -r 00d309722520 -r e494ada70bea MHMC/2024-04-16/notes.xml --- /dev/null Thu Jan 01 00:00:00 1970 +0000 +++ b/MHMC/2024-04-16/notes.xml Fri Apr 19 15:09:59 2024 +0100 @@ -0,0 +1,261 @@ + + + + + + + MHMCC Minutes 2024-04-16 + + + + +

;; Last edited: Tue Apr 16 18:24:01 2024ore Agenda Edinburgh Meeting +House Management Committee Henry S. Thompson, Convenor Tuesday 16 April +5:15 p.m., in 7 Victoria Terrace

+

Zoom link: +https://us02web.zoom.us/j/81467950877?pwd=VGg1U3h3K095bWFLUCsveHZyNmhrdz09

+

Present: Rachel Fitzgerald, Miranda Girdlestone, Jacqueline Noltingk, +Henry S. Thompson Prevented: Copies to: Neil Turner, Susie Harding

+
    +
  1. Opening worship

  2. +
  3. Project updates: 2.1 CVenues

  4. +
+

Ongoing back-and-forth with Hartley Kemp (HK) of CV getting details +of the building to him, in preparation for the full formal License +Agreement. Some niggles to still be sorted including Emergency Lighting +and weight bearing capacity of the Meeting Room, cleaning costs. HK will +be visiting on Monday 22 April to attempt to reach final agreement on a +draft to send to Trustees.

+

CVenues will be in from 14 July – ??

+

See option 2 in the attached plan for the planned Meeting Room +layout. Scrim across the room just E. of the main door on Sundays.

+

We have the Meeting Room, Kitchen and access from 0900–1400.

+

Wednesday Meeting will be in Johnstone Terrace Wildlife Garden / the +Palm House. Childrens’ Meeting have been offered one day there if they +would like.

+

HST will brief Central Edinburgh at Local Meeting on ? 6 June

+

ACTION: MG to check with City of Edinburgh about a) the validity span +of an EICR; b) the need for emergency lighting to be checked to a +standard.

+

2.2 Hideout Cafe

+

Hideout Cafe have not replied to our most recent proposal. We are +going forward on the assumption that they are no longer interested. +Their main interest was always in the full refit/more room/plumbing etc. +version.

+

We have considered the possibility of looking for someone else to do +just-a-pop-up, but decided enough work is pending, and we may get the +information we wanted from a trial run if CVenues try something.

+

Hartley Kemp has been informed. We won’t prejudge the possibility of +him doing something along similar lines until we’ve talked with him on +Monday.

+

2.3 Lighting See attachment 1

+

Majk Stokes managed gathering quotes. MG and MS judged the Gunn and +Alexanders quote to be appropriate considered. Additional complexity +with Mark Kisby’s involvement to manage the physical interaction of +their hanging and the lighting. There is also the question of the +quality of microphone system and whether we should do something about +this.

+

MG will call Mark K to come and explore the lighting/microphone +interaction and suggest and quote for a solution, possibly on 22 April +if he can make.

+

We should consider also inviting Mark Kisby to attend at some event +where we suspect the problems would manifest and observe.

+

We agree to ask Trustee’s approval for asking Keith Gunn to go ahead +per their quote.

+

2.4 Carpets See attachment 2

+

Two quotes for Carpet or Carpet Tile, without floor preparation.

+

At least 10-year wear.

+

Carpet tile has the advantage of allowing square-by-square +replacement in case of damage or stain.

+

‘Stain-free’ has strong smell at first, possible health and +environmental issues.

+

MG to try to get a look at an existing installation of tile with some +years of use wrt possible lifting at the edges under wear.

+

ALthough vinyl is cheaper as such, the preparatino is much more +substantial, so roughly double the cost for the Foyer (6k vs. 3k).

+

We agree to return to this once we get the information we need to +choose, both wrt tile vs. carpet and with respect to the Foyer.

+

2.5 Period products See attachment 3

+

Quotes from three outfits, MG recommends Hey Girls, who also have the +contract for the City of Edinburgh. RF says they are used in AU.

+

We agreed that MG should go ahead and contract with Hey Girls for +installations in all toilets.

+

2.6 Flat 3F2 at 6 Upper Bow

+

HST to explore offering 3F2 to Hartley 1) Check with City re Short +term lets regulation 2) Check with Clan Gordon about whether they would +manage Then bring this back for consideration.

+

If not viable, then ask CG to get quotes for the options they +recommend.

+
    +
  1. Time without staff
  2. +
+

We have had time without staff.

+
    +
  1. Date of next meeting
  2. +
+

30 April 2024 1715, 7 Victoria Terrace

+ +